Search

Huge beams for Norwich Northern Distributor Road will mean disruption for drivers on A47 next week

PUBLISHED: 16:41 09 March 2017 | UPDATED: 08:19 10 March 2017

The Norwich Northern Distributor Road (NDR) takes shape. Pic: Mike Page.

The Norwich Northern Distributor Road (NDR) takes shape. Pic: Mike Page.

Mike Page

Drivers have been warned that they are likely to face disruption next week - when huge steel beams for the Norwich Northern Distributor Road are brought into the county.

And, next month, trains will have to be cancelled between Norwich and north Norfolk for one or two Sundays, while the beams are hoisted into place.

The delivery of the 36.7m steel beams for the bridge, which will carry the £178.5m road over the Norwich to Sheringham railway, had been due this week.

But police elsewhere in the country were unable to provide an escort for the five lorry loads of beams, so they will now travel to the county next Tuesday, Wednesday and Thursday.

The beams are being transported from Middlesbrough and will travel along the A1, A47 and B1140, through Panxworth, before the reach the bridge site from Plumstead Road.

Plumstead Road will be closed for around 15 minutes for each arrival, which should happen between 12pm and 4pm on each of the days.

The beams - five braced pairs - will arrive in halves and, after assembly on site will be lifted into place on Sunday, April 9 and/or Sunday, April 16.

Bittern Line trains will be replaced by buses on those days.

Meanwhile, a number of road closures, as well as frequent use of temporary signals, will be needed over the coming weeks as construction of the NDR continues.

Closures on Drayton Hall Lane will continue until March 24, for traffic calming work including road narrowing and chicanes.

From Monday, March 20, Drayton Lane South will be closed for seven weeks until May 5 so roundabouts can be installed.

Holt Road will be shut for a week from April 3 until April 7 and Reepham Road for three weeks from April 17 until May 5.

Buxton Road will close for three weeks from May 8 until May 26.

Norfolk County Council and Balfour Beatty apologise for what they described as “unavoidable disruption” to travel during construction of the road.

Once complete, the Northern Distributor Road will stretch from the A47 at Postwick to the A1067 Fakenham Road.


If you value what this story gives you, please consider supporting the Norwich Evening News. Click the link in the yellow box below for details.

Become a supporter

This newspaper has been a central part of community life for many years, through good times and bad, serving as your advocate and trusted source of local information. Our industry is facing testing times, which is why I’m asking for your support. Every single contribution will help us continue to produce award-winning local journalism that makes a measurable difference to our community.

Thank you.

Most Read

Most Read

Latest from the Norwich Evening News